The scope of Electrum works included:
1. Implementation of external lighting of the station.
2. Implementation of earthing system.
3. Securities exchange in the fields drainage 15kV switchgear (installation and start-up of security fields such Micom P139).
4. Securities exchange in the fields of functional switching 15kV (installation and commissioning of security fields such Micom P139).
5. Implementation of control cabinets for the 110kV (overcurrent protection, distance security and transformers protection made on the type of security Micom).
6. Installation and start-up of control cabinets (110kV line fields, 110/15kV transformer fields, the coupling field on the 110 and 15kV).
7. Installation and start-up of the “own needs” cubicles.
8. Implementation and start-up of the telemechanics system.
9. Fabrication and installation of cable racks in the 110kV switchgear.
10. Cabling and wiring of the secondary circuits in 110/15kV switchgear (line fields 110kV, 110kV field coupling, transformer boxes, fields, linear and functional 15kV switchgear).
11. Implementation of lighting, sockets and heating of control station and 15 kV switchgear.