Usable area 65,000m². Project and realization of a complete object-oriented automatics system with prefabrication of power-steering cubicles, equipment assembly, installation assembly, programming of controllers, starting the whole system in an automatic mode and BMS system realization.  

The following work is included in our contract:

  •  Supply and installation of a wiring system,
  •  Installation of measurement devices,
  •  Assembly, supply and installation of power-control switchgears of ventilation systems,
  •  Assembly, supply and installation of control panels for fan-coil systems and heaters – 811 units,
  •  Assembly, supply and installation of monitoring cubicles (data acquisition),
  •  Electrical measurements and system start-up in manual mode,
  •  Calibration of servo-motors as well as configuration of inverters,
  •  Configuration of digital controllers and XT communication extension modules,
  •  Collaboration in the design process,
  •  Collaboration in implementation of the BMS system
  • Collaboration in activation of power-control cubicles
  •  Collaboration in activation of automation control rooms,
  • Installation of CO detection and generator oil leakage system.