RONDO 1 in Warsaw
Usable area 65,000m². Project and realization of a complete object-oriented automatics system with prefabrication of power-steering cubicles, equipment assembly, installation assembly, programming of controllers, starting the whole system in an automatic mode and BMS system realization.
The following work is included in our contract:
- Supply and installation of a wiring system,
- Installation of measurement devices,
- Assembly, supply and installation of power-control switchgears of ventilation systems,
- Assembly, supply and installation of control panels for fan-coil systems and heaters – 811 units,
- Assembly, supply and installation of monitoring cubicles (data acquisition),
- Electrical measurements and system start-up in manual mode,
- Calibration of servo-motors as well as configuration of inverters,
- Configuration of digital controllers and XT communication extension modules,
- Collaboration in the design process,
- Collaboration in implementation of the BMS system
- Collaboration in activation of power-control cubicles
- Collaboration in activation of automation control rooms,
- Installation of CO detection and generator oil leakage system.